Managing the pipeline is concerned with achieving 3 things:
- policy and idea generation while balancing the risk of too many against too few potential work components
- having a controlled entry point to the portfolio and for the authorisation of work
- setting up work components to succeed by being clear about the problem to be solved (or opportunity to be exploited) and devoting sufficient attention to programme and project initiation and development
This can be achieved by having a set of criteria, both for selection as a prioritised work component and for the portfolio itself. Before a work component is considered for authorisation, the portfolio manager should ensure that an impact assessment is conducted of financial, resource and technical capability and availability, and that the programme or project does not duplicate other related work.
Authorised entry into the portfolio should be aligned to the initial decision point for starting the first phase of a programme or project. At this point, the decision is not based on a business case but instead on the approval of the programme or project brief (see Chapter 14: Programme and project life cycles).
This decision is concerned with confirming there is a real policy need or opportunity which needs addressing now and that:
- the envisaged outcome is desirable
- the work can be justified
- risks have been identified and are acceptable or can be mitigated
- the solution is (or if not known, is likely to be) acceptable
- funding and resources are available to complete the work and support any outcomes
- there is an outline plan for the work
This involves reviewing the vision, justification and outcomes for a programme or project together with any strategic assumptions before any funding and resources are committed (see Chapter 15: Managing a programme or project).
At this point, the portfolio director should ensure that an appropriately skilled and experienced senior responsible owner and programme or project manager have been appointed.
Government Major Projects Portfolio and appointing senior responsible owners
Programme or projects in, or expected to join, the Government Major Projects Portfolio should appoint the senior responsible owner, by letter, jointly from the accounting officer of the sponsoring organisation and the Government Head of Project Delivery Function (or as delegated to the Government Head of Profession for Project Delivery). The letter should be published on GOV.UK. See The role of the senior responsible owner for more information.
Departmental Major Projects Portfolio and appointing senior responsible owners
Programme or projects in, or expected to join, the Departmental Major Projects Portfolio should appoint the senior responsible owner by letter from the accounting officer of the sponsoring organisation. See The role of the senior responsible owner for more information.
When authorising the start of work, the portfolio director and any relevant boards should clearly define the tolerances and constraints that the senior responsible owner should operate within. Work should be authorised on a phased basis to contain risk by limiting the amount of expenditure and effort until enough information is available to make a decision on whether the work should continue. As such, the portfolio manager should ensure that each work component has an integrated assurance and approval plan and that this aligns with the decisions expected from the portfolio director and relevant decision-making body (for example, an investment committee).