A plan sets out how objectives, outcomes and outputs are to be delivered within defined constraints, in accordance with the strategy agreed for the portfolio, programme or project. A plan provides the basis for decision-making on investment and approvals, for example a programme or project business case or a portfolio investment bid.
Planning identifies the considerations for delivery so that these can be managed in an integrated way through the life cycle, as a portfolio, programme or project plan. This approach is often known as integrated or consolidated planning.
A portfolio plan (also known as a delivery plan) supports the organisation’s strategic objectives and is developed on a cyclical basis as part of organisational business planning, for example as part of a spending review or the annual business planning cycle. Once approved, the portfolio plan is baselined, with subsequent changes managed through change control (see Chapter 22: Change control) until the next planning review.
A programme or project plan (also known as a delivery plan) is developed on a progressive basis from initiation onwards and covers both the development and delivery of the work through the life cycle. The programme or project plan should provide a robust basis for decisions on investment to be taken at the appropriate point in the life cycle. This does not mean work needs to be planned in detail from end to end, as this is often not feasible, for example in large multi-phase programmes, or inappropriate, for example in agile delivery. The plan for a current phase should be in enough detail to enable decisions to be made and progress to be tracked. Plans for later phases can be in outline, with governance and approvals tailored accordingly.
Once the full business case is approved, the programme or project plan is baselined, with subsequent changes managed through change control until the work is completed. Detailed plans for individual projects or work packages can be developed iteratively, within the constraints and tolerances agreed for the business case and overall plan.
A plan should include the proposed scope of the work to be delivered to achieve the objectives, particularly:
- outputs and outcomes, what is to be delivered, by who and when by?
- benefits, what benefits are to be realised, by who and when by?
A plan should also include the anticipated constraints, particularly:
- time, how long should the work take to develop and to deliver?
- resources, what people, facilities and equipment are needed to undertake the work?
- cost, what funding is needed, when and where from?
- risk, assumptions and dependencies, what are they, how might they affect the plan and how can they be managed?
- issues, what are they, how do they affect the plan and how can they be managed?
- quality, how much features and characteristics of an output bear on its ability to show that it meets expectations or stated needs, requirements or specification?
A plan should not only cover the work needed to deliver, build or develop the outputs, but should build on the delivery strategy and cover aspects such as:
- approvals and assurance, what is required, from whom and when? (see Chapter 4: Governance and management)
- procurement, if commercial arrangements are needed to deliver or operate the solution, what procuring activities are needed including timescales (see Chapter 25: Procurement and contract management)
- stakeholder engagement, how stakeholders will identified and engaged throughout? (see Chapter 26: Stakeholder engagement)
- communications, the information that will be shared with stakeholders and how? (see Chapter 27: Communications)
- verification and validation, how the solution will be checked against the specification and confirmed as fit for purpose (see Chapter 34: Verification and validation)
- change and transition into use, the activities needed to embed change and move the solution into use (see Chapter 35: Management of organisational and societal change, and Chapter 36: Transition into use)
- use and disposal, additional planning needed for operating and retiring the solution, for example ongoing product and service management, asset management and disposal? (see Chapter 37: Use and disposal)